Cost to Build a 6-Story Concrete Condo in Toronto: $50M–$100M+

Building a 6-storey reinforced concrete condominium in Toronto is a major undertaking. Current market estimates (2024) range CAD $50 million to over $100 million, depending on:

Key Cost Drivers

  • Size & complexity: 50 vs. 150 units; amenity level; architectural expression.
  • Site conditions: Soil (shoring, dewatering), contamination, access, heritage adjacency.
  • Materials & labor: Concrete ($250–350/m³), rebar, formwork; trades shortage drives premiums.
  • Location premium: Downtown core vs. midtown vs. Scarborough—land $200–800+/sq ft buildable.
  • Professional fees: Arch, struct, mech, elec, civil, code, sustainability consultants: 8–12% of hard costs.
  • Approvals & permits: Site plan, building permit, development charges (DCs ~$100–150/sq ft GFA), Section 37 benefits.
  • Contingency: 5–10% (higher for complex sites).

Typical Budget Breakdown (Mid-Range, ~80 units)

Category% of TotalEst. CAD
Land25–35%$15M–35M
Hard construction45–55%$30M–55M
Soft costs12–18%$8M–18M
Development charges/fees8–12%$5M–12M
Financing/carry5–8%$3M–8M
Contingency3–5%$2M–5M
Total$63M–133M

Timeline

24–36 months: 6–12 mo pre-con (approvals, sales), 18–24 mo construction, 3–6 mo occupancy/closing.

Pre-sales (70–80% required for construction financing) are the critical path. Engage a qualified development manager early.