Condo Construction Cost per Square Foot in Wyoming (2024)

Building a condominium in Wyoming costs less than the national average, but significant variation exists based on location, specification level, and project scale. Here's the current cost landscape.

Baseline Figures

  • National average (2023–24): ~$185–$210/sq ft (NAHB/RSMeans)
  • Wyoming average: ~$170–$195/sq ft
  • Typical range: $140/sq ft (basic, rural) → $250+/sq ft (luxury, Jackson Hole)

Key Cost Drivers

Project Budget Example (Mid-Market, 4-Story, 50 Units, Casper)

  • Hard costs: $185/sq ft × 55,000 GSF = ~$10.2M
  • Soft costs (design, permits, fees, financing, marketing): 25–30% = ~$2.8M
  • Land: Highly variable
  • Contingency: 5–10%
  • All-in: ~$220–250/sq ft including land & soft costs

Wyoming-Specific Considerations

  • Energy codes: 2021 IECC adoption increases envelope/insulation costs
  • Wind/seismic: Moderate seismic (Yellowstone zone); high wind design in some areas
  • Workforce housing demand: Teton County mandates inclusionary units or fees
  • Modular/prefab: Gaining traction to mitigate labor shortages; 10–15% savings potential

For accurate budgeting, engage a Wyoming-licensed GC or cost consultant early—state averages mask extreme local variance.

Copyright Wanderlust World © https://www.ynyoo.com
FactorImpact on Cost
LocationJackson Hole/Teton County: 40–80% premium (labor scarcity, material logistics, land cost, strict codes). Cheyenne/Casper: near state average. Rural: lowest.
Building HeightLow-rise (1–3 stories, wood frame): cheapest. Mid-rise (4–7 stories, podium + wood): +15–25%. High-rise (8+, concrete/steel): +40–60%.
Finish LevelBuilder-grade: baseline. Mid-market: +$25–40/sq ft. Luxury (stone, custom millwork, smart home, premium appliances): +$60–100+/sq ft.
ParkingSurface: $3–5K/stall. Structured: $25–40K/stall. Underground: $45–70K/stall.
Site ConditionsRock excavation, high water table, steep slopes, remediation: major cost adders.
Labor MarketWyoming's small contractor base creates bidding volatility; seasonal constraints (winter) compress schedules.